TITAGARH RAIL Q3 HIGHLIGHTS
Sale of wagons to IR was impacted in the current quarter due to inadequate supply of wheelsets from the Rail wheel factory. Due to this the customer has also extended the delivery period
Currently we are in design phase of the orders currently being executed, impacting the revenue numbers. There shall be a uptake in revenue as we start production & deliveries.
Rolled out its first stainless steel metro train set for Bangalore metro on Jan 6, 2025
Production of traction motor ramped up to 100 units per month