
Raven Lites Enterprises
February 12, 2025 at 05:00 PM
THE PROCESS OF BOREHOLE DRILLING.
STEP 1: HYDROGEOLOGICAL/ GEOPHYSICAL SURVEY:
We employ both Digital and Old methods.
This gives;
✔Borehole depth,
✓ Expected yield
✔Expected Water Quality
TIMELINE: Exercise 1 day, Report 3 Days
STEP 2: DRILLING APPROVALS AND PERMITS:
The necessary approvals includes; ✓Environmental Impact Assessment (EIA) for NEMA license.
✔Water Resources Authority (WRA) approval. ✔Water Resources Users Association (WRUA) ✓ Letter of No Objection from the local water provider
✓ County Approvals
TIMELINE: within one month
STEP 3: BOREHOLE DRILLING:
The total cost will be calculated based on the recommendations from the Hydrogeological survey results. This includes;
✓Drilling
✓ Gravels
✓Casing
✓Development
TIMELINE: 5 Days
STEP 4: PUMP TESTING:
Aims to determine the optimum rate at which a borehole should be pumped and yield
TIMELINE: 24 hours
STEP 5: BOREHOLE EQUIPPING AND PUMP INSTALLATION.
This involves installation of submersible pump & motor.
✓pipes
✓ submersible cables,
✓ control panel,
✔Inverter and solar panels (if solar powered).
TIMELINE: For Electricity 1 Days and 3 days for Solar
With availability of resources a borehole can be drilled within 5 to 10 Working days.This includes the drilling,casings, testpumping and water analysis plus pump installation.
Call/Whatsapp for any further clarifications.+254769787989
RAVEN LITES ENTERPRISES
[email protected]