Monday, 24 February 2025:
Loadshedding will be reduced to *Stage 4* from *Monday at 00:30 until further notice.*
This follows the successful recovery of all five units at Majuba, two units at Camden, and one unit at Medupi since Saturday, totaling eight out of ten generation units that had tripped this weekend.
Additionally, emergency reserves replenishment is progressing well. The return of these units comes after identifying the root causes of multiple unit trips, which were unconnected and purely technical in nature, related to electrical and control system issues in auxiliary parts of these power stations.
Planned maintenance stands at 7 706MW. Eskom will provide an update on Monday afternoon.
🇵🇸
🇮🇱
🏳️🌈
👍